Skip to main content

Liens filed on Lowe’s project

2/20/2018

An Albany engineering firm has filed a mechanic's lien against Lowe's and a shopping center developer, claiming that it hasn’t been fully paid for work done in developing construction and site plans for a Lowe’s store in Potsdam, according to an article in the Watertown Daily Times. The disputed amount is $351,235.70, according to the St. Lawrence County clerk's office.

The work started Oct. 7, 2005 and concluded March 11, according to the newspaper. It's the third mechanic's lien filed against Lowe's and Jeda Capital-56 LLC in seven weeks for the Potsdam site, the report said.